On November 2, 2026, the Town of Cary announced that Black Creek Greenway had fully reopened. The project finished seven months ahead of schedule and came in slightly under budget. That same Monday, the Wake County Board of Commissioners approved a $6.6 million construction contract for Lake Crabtree County Park, which sits at the greenway's northern end. Wake County says that work is expected to begin later this year, finish in December 2027, and close parts of the park while it runs.
So the construction fences at the north end aren't going away. They're moving from Cary's side to the county's. For about a year, the trail's last stretch is better used as a way into William B. Umstead State Park than as a lap around the lake.
Two and a half years, three closures, one trail again
The renovation covered roughly 2.5 miles between Old Reedy Creek Road and West Dynasty Drive. Cary built that section more than 25 years ago. Construction began June 4, 2024, with about three years planned. Cary closed the trail one section at a time and left the rest open, which is why the work felt like a moving detour more than one long shutdown:
- West Dynasty Drive to Livingstone Drive reopened August 29, 2025.
- Livingstone Drive to Weston Parkway closed in the first week of September 2025. It reopened in early May 2026, along with the new Cary Parkway pedestrian bridge.
- Weston Parkway to the Old Reedy Creek Road Trailhead closed May 4, 2026. The Town's schedule had pegged this last phase for 2026 to 2027. In May, The News & Observer reported that it was expected back sometime in winter. Cary's project page marked it fully reopened on October 30.
The Town credits the early finish to a phasing plan worked out with the contractor. The plan skipped the slow winter construction months, which also cut costs. Final construction costs are estimated at about $17.3 million, against an original bid of nearly $17.5 million.
What feels different underfoot
The renovated stretch is now 12 feet wide, bridges included, to meet Cary's current greenway design standard. Crews also straightened some of the sharper curves and rebuilt the drainage. Cary's main greenway page still lists the route as 10-foot asphalt, so the extra width only applies to the renovated 2.5 miles.
Two changes stand out more than the width.
The Dynasty Drive climb is gone. You used to leave the woods for a steep 0.4-mile sidewalk along West Dynasty Drive between two sections of trail. A new quarter-mile of greenway now crosses Dynasty Drive directly, keeping a manageable grade for cyclists and staying in the woods.
Cary Parkway has a bridge with something to look at. The pedestrian bridge is 285 feet long and stands about 50 feet above Black Creek. It's part of a 650-foot sidewalk connection, and it opened alongside a new pedestrian signal at Cary Parkway and Norwell Boulevard. The panels are a public artwork by Vicki Scuri titled "Bridge within Nature | Nature within Bridge." Large steel leaf shapes, perforated with circles that change size, frame views of the trees and throw shifting patterns of light and shadow. Accent lighting picks them out after dark. The greenway itself is open dawn to dusk, so the lit panels are mostly something drivers on Cary Parkway see.
Cary's transportation director, Cassie Schumacher-Georgopoulos, said in the Town's announcement that the reopening "restores an important connection for residents and visitors while making the trail safer and more accessible for everyone."
The north end is where the handoff happens
Cary describes the whole route as 7.1 continuous miles. It runs from the Old Reedy Creek Trailhead near Lake Crabtree to Bond Park, where it meets White Oak Creek Greenway. The southern end has been stable throughout. The northern end has been in flux since well before this summer's closure, and it will keep changing after the reopening.
Here's where each piece stood at the north end as of early November 2026, according to Cary, Wake County and NC State Parks:
| Destination off the north end | Status as of early November 2026 |
|---|---|
| Old Reedy Creek Road Trailhead, 2139 Old Reedy Creek Road | Open, with 82 parking spaces, a restroom, a drinking fountain, a bike repair station and a shelter |
| Umstead's Reedy Creek Multiuse Trail | Reached by 0.6 miles of Old Reedy Creek Road, gravel past the I-40 bridge. The trail is 3.7 miles one way and open to bikes, horses and hikers |
| Lake Crabtree Lake Trail | A six-mile hiking loop that takes 2.5 to 3 hours. Bikes are allowed only on the eastern side, which is part of Black Creek, and on the link to the trailhead |
| Lake Crabtree's former multi-use trails | Closed since June 1, 2025 |
| Lake Crabtree fishing pier | Listed by Wake County as closed for repairs in October and November 2026 |
| Lake Crabtree boat rentals | The 2026 season ended September 7. Public boat launches are year-round |
| Lake Crabtree renovation | Approved November 2. Construction is expected to start later this year and finish in December 2027 |
The mountain bike change came first and has lasted longest. Wake County says the park's 148-acre network of mountain bike and hiking trails closed June 1, 2025, after the airport authority declined to renew that lease. Riding moved to the separate 151-acre parcel known as the 286 property. That trail system is now called Haleys Branch. The county plans for it to take in leased Umstead land next to the 286 property as well. The county's directions send riders from the Old Reedy Creek parking lot across the I-40 bridge and down the gravel road. The county also warns that parts may close temporarily for construction, maintenance or removal of structures. Wake County suggests a 10-mile ride from the Lake Trail out to those trails and back.
What the county is building next door
The Lake Crabtree project centers on a 4,805-square-foot education building near the water. Plans call for a classroom for up to 86 people, a covered deck over the lake, restrooms and storage for lake programs. The county is also adding a stormwater wetland beside the building, public art, accessible walkways between the main features, more parking at the boat ramp, a new 724-square-foot restroom, and new roofs on the administration and maintenance buildings. The 2018 parks bond pays for it.
The park manager, Susan Jones, told Wake County that the park has drawn more than 250,000 visitors in 2026. She said:
"These updates will greatly improve accessibility, help us provide programming year-round and create new ways for people to enjoy a park they already love."
The county will post updates at wake.gov/parks/lakecrabtree and on the park's Facebook page. In regular operation, the park is open 8 a.m. to sunset. It closes on Thanksgiving, Christmas Eve, Christmas Day and New Year's Day.
Using the trail this winter
The steady option at the north end is the trailhead and the gravel road beyond it. Umstead's Reedy Creek side has its own entrance at 2100 N. Harrison Avenue in Cary. Its gates are open 8 a.m. to 6 p.m. in November and December, and the park closes on Christmas Day. Cary's page notes that its north end links to Reedy Creek Greenway, which continues through Umstead. The East Coast Greenway Alliance's Cross-Triangle itinerary recommends wider tires for the crushed gravel there.
Cary lists several access points along the way. Each one gives you a different starting length:
- Bond Park, from the Boathouse or Community Center lots, where Black Creek meets White Oak Creek Greenway
- The Black Creek lot on Maynard Road, across from Godbold Park
- Godbold Park's own parking
- North Cary Park, where a 0.4-mile park trail leads to the greenway
- Neighborhood connections at Livingstone Drive and Homestead Drive south of North Cary Park, and at Weston Parkway, Tynemouth Drive, Linton Banks Place and Midenhall Way near the Lake Crabtree end
The trail allows walking, running, cycling, leashed dogs, strollers and wheelchairs, though Cary notes some sections may be too steep for wheelchair users. Its connections include the Cary Dog Park, Cary Action Sports, Northwoods Greenway and Oxxford Hunt Greenway. Cary's plans have White Oak Greenway eventually linking Bond Park to the American Tobacco Trail as one continuous trail. That puts Black Creek in the middle of the East Coast Greenway's route through Cary.
For a breakfast stop, the East Coast Greenway Alliance points riders to Brigs at the Crossing in Maynard Crossing, close to the Maynard Road lot. The restaurant lists its address as 1225 NW Maynard Road and its hours as 7 a.m. to 2:30 p.m. daily.
Cary's official celebration comes on January 1, 2027. The reopening will be part of the Teen Council's annual First Walk, which starts at 10 a.m. at North Cary Park. A December 2017 Town newsletter described an earlier First Walk as an hour on Black Creek Greenway, starting at North Cary Park's entrance and led by Greenways Committee members and the Teen Council. The reopening comes in the year Cary passed 100 miles of greenways. For more on how the trails fit into a Cary weekend, see our guide to Cary parks, greenways and local spots.
If a walk to a greenway access point is part of what you love about your street, it's also part of what your home is worth. Charles Christiansen knows the neighborhoods along Black Creek, from Bond Park up to Weston Parkway. To see how your home stands today, get your instant home valuation, or browse more on Cary neighborhoods.